WIP Explained: What Every Brisbane Construction Business Owner Should Understand

If you run a construction business, your Profit and Loss Statement doesn't always tell you the full story.
You might have several projects underway, significant progress claims going out and plenty of work in the pipeline, but still find it difficult to answer a relatively simple question:
How much profit are we actually making on each job right now?
That's where Work in Progress, or WIP, becomes important.
For builders and construction businesses, accurate WIP reporting helps connect what's happening on site with what's appearing in your financial reports.
When it's done properly, it can give you much better visibility over project profitability, underbilling, overbilling, cost overruns and cash flow.
For Queensland builders, WIP can also form part of the broader financial picture relevant to Queensland Building and Construction Commission Minimum Financial Requirements. The QBCC specifically recognises work completed but not yet invoiced within its guidance on current assets and WIP.
So, what exactly is WIP and what should construction business owners be looking at?
What Is Work in Progress in Construction?
In simple terms, Work in Progress measures the financial position of construction jobs that aren't yet complete.
Construction projects often run over several months or even years.
During that time:
Materials are purchased
Employees and subcontractors are paid
Work is completed
Variations arise
Progress claims are issued
Clients make payments
These events don't always happen at exactly the same time.
That creates a gap between the amount of work you've actually completed and the amount you've invoiced.
WIP reporting helps make that gap visible.
The Queensland Building and Construction Commission describes construction WIP as estimating the asset or liability accumulated from construction contracts based on what the contractor is entitled to invoice for work performed, less what has actually been invoiced at that point.
Why Your Profit & Loss Can Be Misleading Without WIP
Imagine you're halfway through a large construction project.
You've incurred substantial labour, material and subcontractor costs, but your next progress claim hasn't been raised yet.
If you simply look at the accounting system without adjusting for the work completed, the project's financial performance could appear very different from reality.
The opposite can happen too.
You may have invoiced ahead of the physical work completed, meaning there is plenty of cash in the bank even though some of that revenue relates to work you still need to deliver.
This is why builders shouldn't rely solely on:
Revenue
Bank balance
Invoices issued
Total costs incurred
To determine whether a project is profitable.
Cash received, invoices issued and profit earned are different numbers.
Accurate WIP reporting helps bring them together.
Underbilling: You've Done the Work but Haven't Billed It
One of the key things WIP reporting can uncover is underbilling.
Broadly, underbilling occurs when the value of work you've earned or completed is greater than the amount you've billed.
For example:
Your team may have completed a significant stage of the project, but the associated progress claim hasn't yet been raised.
The business has already used cash to fund:
Labour
Subcontractors
Materials
Equipment
Site costs
But hasn't yet invoiced the corresponding amount.
That can place unnecessary pressure on cash flow.
Consistent underbilling can effectively mean your construction business is funding the client's project from its own working capital.
A monthly WIP review can help identify these gaps earlier.
Overbilling: You've Billed Ahead of the Work
The opposite is overbilling.
This occurs when you've billed more than the revenue earned based on the work completed at that point.
From a cash flow perspective, that can initially feel positive.
There may be a healthy amount of cash sitting in the bank.
But that doesn't necessarily mean the money represents profit.
Some of it relates to construction work and costs that are still to come.
Industry guidance describes this distinction clearly: overbilling can mean holding cash for work not yet completed, whereas underbilling can mean you've earned revenue for work that hasn't yet been claimed.
This is why using the bank balance as your primary measure of business performance can be particularly misleading in construction.
How Is Construction WIP Calculated?
There isn't one calculation that suits every construction business.
The Queensland Building and Construction Commission notes that larger businesses may use percentage-complete methods, while smaller businesses may use costs incurred but not yet invoiced, provided the treatment complies with the relevant accounting requirements.
For projects using a percentage-complete approach, one common starting point is:
Costs incurred to date ÷ Estimated total project cost = Estimated percentage complete
For example:
A project has an expected total cost of $800,000.
Costs incurred to date are $400,000.
That suggests the project is approximately 50% complete from a cost-to-cost perspective.
If the total contract value is $1 million, the financial reporting may then recognise approximately $500,000 of earned revenue, subject to the contract and applicable accounting requirements.
If you've only billed $450,000, the project may show $50,000 of underbilling.
If you've billed $550,000, it may instead show $50,000 of overbilling.
The calculation itself isn't the most important part.
What's important is having reliable information supporting it.
Your Estimated Cost to Complete Matters
This is where WIP reporting becomes particularly valuable for business owners.
Imagine you originally expected a project to cost $800,000.
Halfway through, material prices have increased, additional subcontractor costs have appeared and the project manager now expects total costs will reach $900,000.
If your WIP calculation still assumes an $800,000 project cost, your expected margin can look healthier than it really is.
That's why construction businesses need to continually review their estimated cost to complete.
Look at:
Labour remaining
Materials still required
Subcontractor commitments
Equipment and plant costs
Site overheads
Approved variations
Potential rework
Project delays
Other foreseeable costs
The earlier margin deterioration is identified, the more options you generally have to respond.
Variations Need to Be Included Properly
Variations are another common source of inaccurate construction reporting.
During a project, the original contract value may change because of additional or amended work.
But not every variation should automatically be treated as guaranteed revenue.
The financial treatment can depend on whether the variation has been properly documented, approved and whether the business has an enforceable entitlement to payment.
Operationally, this reinforces something we've discussed in other Rise construction articles:
Every variation needs a process.
It should be identified, documented, priced, approved and invoiced appropriately.
Otherwise, builders can end up completing additional work without seeing the profit they originally expected from the project.
WIP and Construction Cash Flow Go Together
WIP isn't simply an accounting exercise.
It's an important cash flow tool.
A good WIP report can highlight situations where:
Work is progressing but invoices are falling behind
Progress claims don't align with costs
One project is consuming significant working capital
Costs have increased faster than expected
Retentions are tying up cash
Billing is ahead of project delivery
These insights can significantly improve cash flow forecasting.
Instead of asking:
"Why is there never enough cash?"
You can begin identifying which project is creating the pressure and why.
WIP Is Also Important for Queensland Builders
For Queensland construction businesses, WIP can also be relevant to the financial requirements associated with holding a QBCC licence.
The Queensland Building and Construction Commission Minimum Financial Requirements include requirements relating to current ratio, Net Tangible Assets and Maximum Revenue. QBCC guidance states that licensees must maintain the required financial position, including a current ratio of at least 1:1 and Net Tangible Assets of at least $0, together with the applicable Maximum Revenue requirements.
QBCC guidance also includes work completed but not yet invoiced among current assets in relevant circumstances and specifically discusses WIP accounting for construction contracts.
That makes accurate construction accounting important for more than simply understanding profit.
It's also part of maintaining reliable financial records as the business grows.
What Should Be Included in a Monthly WIP Report?
The exact report will depend on your business, but for each active project I'd want visibility over:
Original contract value
Approved variations
Revised contract value
Original estimated project cost
Latest estimated total project cost
Costs incurred to date
Estimated cost to complete
Estimated percentage complete
Revenue recognised to date
Progress claims issued
Underbilling or overbilling
Forecast gross profit
Forecast gross margin
Retentions where relevant
You should also be able to compare the current expected margin with the original expected margin.
That's where some of the most valuable conversations happen.
If a project started with a forecast 20% margin and is now heading towards 12%, you need to understand why before the job finishes.
How Often Should Builders Review WIP?
For an established construction business managing multiple active projects, I recommend reviewing WIP monthly.
For large or higher-risk projects, key job-cost information may need to be monitored even more frequently.
Waiting until year-end can be far too late.
By then:
The money may already have been spent
Variations may be harder to recover
Cost overruns may have compounded
The project may already be complete
Margin opportunities may have disappeared
Monthly WIP reporting turns the conversation from:
"What happened?" into: "What's happening now, and what can we do about it?"
WIP Should Help You Run the Business
A WIP report shouldn't simply be something your accountant prepares because the accounting rules require it.
It should help you answer practical questions.
Which jobs are making money?
Look at forecast margins.
Which jobs are consuming cash?
Review underbillings, costs incurred and upcoming claims.
Which projects are slipping?
Compare revised cost-to-complete estimates with the original budget.
Are progress claims keeping up with delivery?
Compare earned revenue with billings.
Can we comfortably take on another large project?
Combine WIP with your pipeline and cash flow forecast.
That's when construction accounting becomes genuinely useful.
Better Business Decisions with Construction Accountants Brisbane
As a construction business grows, the financial side becomes more complicated.
Managing multiple jobs means dealing with different project stages, subcontractors, materials, progress claims, variations, retentions and changing costs simultaneously.
Without accurate WIP reporting, it becomes increasingly difficult to know which projects are actually driving profit and which ones may be quietly eroding it.
As Construction Accountants Brisbane, Rise Accountants work with builders and construction businesses across Queensland to provide accounting and business advisory support that goes beyond tax compliance.
From construction WIP reporting and job profitability to cash flow forecasting, QBCC financial requirements, tax planning and ongoing business advisory, we help construction business owners understand what's really happening behind the numbers.
If you've been searching for construction accountants near me because your business is growing and you need better visibility over individual projects, WIP is one of the first areas worth getting right.
Frequently Asked Questions
What is WIP in construction accounting?
WIP stands for Work in Progress. In construction accounting, it helps measure the financial position of projects that are underway but not yet complete. In Queensland, the Queensland Building and Construction Commission describes WIP as estimating the asset or liability accumulated from construction contracts based on work entitled to be invoiced less amounts already invoiced.
Why is WIP important for builders?
WIP gives builders better visibility over job profitability, underbilling, overbilling, cost overruns and margin changes. Without accurate WIP, financial reports can give an incomplete view of how active construction projects are actually performing.
How often should a construction business review WIP?
For established builders managing several active projects, monthly WIP reporting is a practical starting point. More complex or higher-risk projects may justify more frequent monitoring of costs and forecast margins. Regular WIP reconciliation is widely recommended as a way to identify margin movement and billing issues before year-end.
What is underbilling in construction?
Underbilling broadly occurs when the value of work earned exceeds the amount billed to the client. This can place pressure on cash flow because the builder may already have paid labour, suppliers and subcontractors without raising the corresponding progress claim.
What is overbilling in construction?
Overbilling occurs when billings exceed the revenue earned based on work completed. Although this can create a stronger short-term cash position, the excess shouldn't automatically be treated as profit because the business still has work and costs to deliver.
How do builders calculate percentage complete?
A commonly used cost-based starting point is:
Costs incurred to date ÷ latest estimated total cost = percentage complete.
However, the appropriate WIP method depends on the contract and applicable accounting requirements. The Queensland Building and Construction Commission notes that different approaches may be appropriate for different businesses.
Does WIP affect QBCC financial requirements?
It can. QBCC guidance recognises work completed but not yet invoiced among relevant current assets and WIP among allowable assets in its Minimum Financial Requirements guidance. Queensland licensees also need to maintain the applicable current ratio, Net Tangible Asset and Maximum Revenue requirements.
What should be included in a construction WIP report?
A useful WIP report typically includes contract value, approved variations, costs to date, forecast cost to complete, estimated percentage complete, revenue recognised, progress claims, underbilling or overbilling, expected profit and forecast margin.
Can WIP help identify construction projects losing money?
Yes. Updating the estimated total cost and comparing the revised margin with the original project margin can identify deterioration before the job is complete. This is particularly useful when labour, subcontractor or material costs change during construction.
Is WIP the same as cash flow?
No. WIP measures the financial progress of active projects, while cash flow measures actual money entering and leaving the construction business. Overbilling is a good example of why the distinction matters: cash may have been received even though the corresponding work hasn't yet been earned.
What accounting standard applies to construction WIP in Australia?
The Queensland Building and Construction Commission states that construction WIP should be calculated in accordance with AASB 15 Revenue from Contracts with Customers, which replaced AASB 111 Construction Contracts.
When should a builder speak to a construction accountant about WIP?
It's worth getting help when you're managing multiple active projects, experiencing cash flow pressure, seeing margins change unexpectedly, preparing QBCC financial information or struggling to determine which projects are actually profitable. Ideally, WIP reporting should be established before project volume becomes difficult to manage.